Tuesday, October 20, 2020

METHOD STATEMENT for Installation of copper pipes for ac units

  

METHOD STATEMENT for Installation of copper pipes for ac units  of Work Purpose  Abbreviations copper pipes installation copper tubes welding soldering
METHOD STATEMENT for Installation of copper pipes for ac units  of Work Purpose  Abbreviations copper pipes installation copper tubes welding soldering

PROCEDURE FOR REFRIGERANT COPPER PIPING

TABLE OF CONTENTS

 

 

1. Purpose …………………………………………………………………………………….…4 

2. Scope ……………………………………………………………………………………...….4

3. ABBREVIATIONS…………………………………………………………………………...4

4. REFERENCES ……………………………………………………………………………….4

5. Responsibilities ………………………………………………………………………………4

6. SAFETY………………………………………………………………………………………6

7. PROCEDURES………………………………………………………….…………………... 7

8. EVACUATION PROCEDURE …………………………………………………………...…9

9.HANDLING AND STORAGE ………………………………………………………….…10

10. ATTACHMENTS …………………………………………………………………….……9

1.      PURPOSE

 

The purpose of this procedure is to describe the quality control procedure to be followed

During installation of Refrigerant Copper Pipes at Community project and to detail the instructions to be followed and the documentation to be employed in order to ensure that safe installation is executed in accordance with the project specifications and standards.

 

 

2.      SCOPE

 

 

The scope of this procedure is to define all activities and requirements necessary for Refrigerant Copper Pipes, Heating, Ventilation and Air Conditioning (HVAC) System at ‘and to ensure that all works/activities, acceptance criteria, IFC drawings, specifications codes community project in  and to ensure that all works/activities are in full compliance with project specifications, drawings and HVACMEP standards related to installations standards, verifying  Documents comply with HVACMEP Typical Inspection Plan (HVACMEPTIP) related to installations.

 

3.      ABBREVIATIONS:

 

 

HVACMEPIC               : HVACMEP Inspection Checklist

HVACMEPTR              : HVACMEP Test Report

SATIP                            : HVACMEP Typical Inspection Plan

HVACMEPES               : HVACMEP Engineering Standards

ITP                                : Inspection & Test Plan

NCR                               : Non Conformance Report

PPE                                : Personal Protective Equipment

QA/QC                         : Quality Assurance/Quality Control

 

4.      REFERENCES

 

§  ANSI B31.5 – Refrigeration Piping.

§  ASHRAE Handbook – HVAC Applications, Systems and Equipment, Fundamentals and       Refrigeration.

 

§ HVACMEPES -001              Heating, Ventilating and Air-Conditioning

 

§ HVACMEPES-    100           HVACMEP Mechanical (HVAC) Code

 

 

5.      . RESPONSIBILITIES

 

5.1  Construction Manager

 

1.To ensure that all preparation and application works are carried out according to

That contact specifications, method statement, and HVACMEP Engineering Specification and manufacturer data sheet.

2.     To ensure that the progressing of work is carried out according to the planned program and as per the approved Method Statement

3.     To ensure that all the manpower, equipment and materials required to execute theWork are available.

4.     To ensure that all related quality procedures are practiced and implemented

5.     To ensure that all safety matters related to this procedure are being observed

5.2  QC Inspector

1.   To ensure full compliance of the work with the related approved method statement

2.   Responsible to ensure that the correct, approved pipe size, dimensions.

3.   Ensure that IFC drawings, Shop drawings displayed on site during installation inspection. 

4.   Ensure that the materials being delivered to site and used are in accordance with The project specifications and approved material submittal and material receiving RFI.

5.   Shall be responsible for the inspection, preparation of RFI all documents and compiling them for the inclusion in the final documentation packaged.

6.   To maintain comprehensive inspection and test records for the purpose of Reference and documentation.

7.   Ensure arrangement and location of latest released for construction drawings, and specifications.

8.   Ensure that tools/ equipment used for testing and commissioning purpose is calibrated and certificates available. (Certificate of calibration tool will be provided during inspection time separately).

5.3  Site Engineer

 

1.Coordinate all the site activities accordance with approved IFC, Shop drawings, project specification, approved method statement and HVACMEP Engineering Standards.

2.To provide all necessary information and distribute responsibilities to his team

3.To monitor the progress of work in relation with work program and to report to The PM.

4.To ensure that the installer is well trained for this type of work.

5.To coordinate with safety officer and to ensure that the works are carried out in safe practicing method.

6.Site engineer shall inform mechanical Quality Control Inspector for internal inspection to check work has been done accordance to IFC & Shop Drawings, HVACMEP standards prior to preparing internal RFI for inspection and the time schedule.

 

5.4 The safty Engineer

 

 

1.Ensure that the work is performed under the safety measures of the approved HSE plan Prior to the commencement of any activities, work force will receive Tool Box on the project safety requirement. This tool box talk will include both activity issues as well as general safety requirements.

2. To maintain continuous inspections of the site activities, advise and train the Involved personnel on daily basis to prevent accidents, personal injury or Property damage

5.5 Site Supervisor/Foreman

 

1.   Shall have the knowledge of installation of copper Piping system in order to explain the method statement to his subordinates.

2.   To ensure that work is carried out properly and according to manufacturer recommendations and instructions received from the site engineer

3.   To ensure that tools, labor and materials are available

 

6. SAFETY

 

1.      Prior to the commencement of any activities the work force will receive Tool box Talk on the project safety requirements. This tools box talk will include both activity issues               as well as genral safety requirements

2.      Direct supervisor will ensure that Protection Equipment’s, PPE, are used by site Personnel at all times during this activity

3.      Coordinate fully with the safety officer in order to maintain safe working Condition and proper housekeeping of the site.

4.      All equipment and accessories have been certified for their capacity and integrity.

5.      Safety and risk assessment shall be performed for every job or task, which has the potential for harm.

6. All personal are issued with personal protection equipment.

7.      Provide hand gloves and educate workers for safe operation.

8.      Always keep the gas cylinder in vertical position.

9.      Always keep fire extinguisher during brazing.

 

7. PROCEDURES:

 

1.       Take extreme care to keep refrigerant tubing/piping clean and dry prior to installation.  The following procedures should be followed:

2.      Check approval of working drawings.

3.      Check size and route of piping for laying refrigerant pipe as per approved IFC drawing.

4.      Install the supports for pipe and check the levels.

5.      Clean thoroughly the outer face of pipe and inner face of pipes and fittings by blowing air or brushing. Prior to copper joint brazing all cuts pipe ends and particularly those immediately upstream of devices should be completely de-burred and any distortion in bore diameter shall be rectified.

6.      Install the refrigerant pipe care should be taken to ensure that the flow and regulating devices (filter/drier, sight glass, solenoid valves, isolation valves (only for large capacity units)) are installed correctly with respect to flow direction.

7.      Flush the entire pipe system with nitrogen gas at 150 – 200 psig to remove all debris inside the pipe.

8.      Carry out the pressure test by using Nitrogen gas at 250psi and for 24 Hrs. for check the leakage and soap solution will be applied in case of leak.

9.Record the reading in the pressure test report.

10.  Provide pipe insulation and cladding for external refrigeration pipe with the specified insulation material.

11.  Vacuum the system to 29 in. HG for 24 Hrs.

12.  Break the vacuum using Refrigerant up to its standing pressure to Zero (Operation Pressure).

13.  Charge the system with refrigerant up to its standing pressure (operating pressure).

14.  System is ready for start-up, commissioning and record the data.

15.  Use only refrigeration grade copper tubing, properly sealed against contamination.

16.  The horizontal sections of the suction line should always slope towards the condensing unit.  There should be 1/2-inch drop for each 10 feet of line, which is sufficient to return oil.

17.  Suitable P-type oil traps should be located at the base of each suction riser.

18.  The oil trap can be constructed with three elbows and is installed at the base.

19.  No trap should be placed directly ahead of the compressor.  This is to prevent slugging of the compressor with oil or liquid refrigerant trapped there.

20.  Suction lines must be insulated with closed cell (min. 3/4" thick) elastomeric thermal insulation to prevent condensation.  Liquid lines require no insulation unless they run through high temperature areas.

21.  Always consult with the concerned engineer for more detailed piping method according to site applications.

22.  All piping should be kept short and with as few fittings as possible.  This is to prevent excessive pressure drop in the lines.  Do not clamp the lines together without insulation, unless it is necessary to use them to provide a heat exchanger.

23.  Lines should never be left loose or unsupported.

24.  All Refrigerant line shall be purged with 7 Kpa gauge (1.0 psig) dry nitrogen while soldering, brazing or welding connections.

25.  Refrigerant piping and tubing shall be securely fastened to a permanent support within 6 feet (1.8m) following the first bend in such tubing from the compressor and within 2 feet (610mm) of each subsequent bend or angle.

26.  Refrigerant piping shall not be located within a required exit.

27.  The direction of flow and Type of line shall be indicated on refrigerant piping.

28.  Before joining 2 metals together, be sure the surface is free from grease, rust and oxides.

29.  Location of stand casing / holder for gas cylinder shall secured.

30.   Personnel to perform brazing/welding shall be certified prior to commence of any brazing / welding activities.

9.      EVACUATION PROCEDURE

·   After the piping pressure test is completed, dehydrate the system by placing a vacuum of 1.7 kpa (0.5in Hg) absolute pressure.

 

·   Remove cores from the service valve.

 

·   Connect the low side of manifold gauge set with Y. HVACMEPE in-line tee to vapor line service valve.

 

·   Connect the high side of the manifold gauge set to liquid line service valve.

 

·   Connect micron gauge available connector on the Y. HVACMEPE in-line tee.

 

·   Connect the vacuum pump to the center port of the manifold gauge set.

 METHOD STATEMENT for Installation of copper pipes for ac units  

·   Open both manifold valves and start the vacuum pump.

 

·   Evacuate the system to at least 500 microns.

 

·   When the system has reached 500 microns, perform the following:

  METHOD STATEMENT for Installation of copper pipes for ac units 

-    Close manifold gauge valves

-    Close valve on vacuum pump

-    Tum off vacuum pump

-    Disconnect manifold gauge center port hose from vacuum pump

-    Attach manifold center port hose to a dry nitrogen cylinder with a pressure set to 165psig and purge the hose.

-    Open the manifold gauge valves to break the vacuum in the line set.

-    Close the manifold gauge valves.

·   Shut off the dry nitrogen cylinder and remove the manifold gauge hose from the cylinder. Open the manifold gauges to release the dry nitrogen from the line set.

  METHOD STATEMENT for Installation of copper pipes for ac units 

·   Repeat the evacuation process two more times. On the third time, allow the vacuum pump to run an additional of 30min after the system reached 500 microns.

 

·   After 30min:

 

-    Close the manifold gauge valves

-    Close valve on the vacuum pump

-    Close the manifold gauge valves

-    Tum off vacuum pump

-    Let the system stand for 15min

-    Close the manifold gauge valves

·   The micron reading should not increase more than 500 microns in 15 minutes.

If it does, then there is either a leak or there is moisture in the system. In case of leak, repair the source of leak and then repeat the triple evacuation process.

 

·   Hold vacuum for 24 hours or cycle vacuum and dry nitrogen purge according to manufacturer recommendations.

 

·   When the pressure requirement is met, disconnect the manifold hose from the cylinder. Perform the following:

  METHOD STATEMENT for Installation of copper pipes for ac units 

-           Close the manifold gauge valves

-  Reinstall service valve cores by removing the manifold hose from the service valve. Quickly install cores with core tool while maintaining a positive system pressure.

-           Charge system with quantity and type of refrigerant as per manufacturer requirements.

 

10.  Handling and Storage

 

on receipt of the refrigerant copper pipes and accessories at site necessary precautions shall be taken for unloading, shifting and storage as follows:

1.all refrigerant pipe and its accessories shall be inspected, handled and stored properly upon receipt at site.

2.it shall be stored in aplace free of water, dust and adequately covered to avoid and kind of damages.

3.all insulation material shoall be inspected for the thickness and densities.

4.while unloading, shifting and storage, it should be ensured that there are no transit damage.

5.any discrepancies, damage, and etc. found to the material will be notified and reported to qa/qc engineer and project enginner for further action.

6.material found not suitable for site use should be removed from site immediately.

7.all material to be used shall be as per approved.

 

11.  ATTACHMENT


Featured Post

Installation operating Maintenance Instructions Radial roof fan

 Installation, Operating and Maintenance Instructions for Radial Roof Fans DRH-Minivent DRH DRV-Minivent DRV DRVF DRVF-H  Installation, Oper...