METHOD STATEMENT for Installation of Air Cooled Condensing Unit (ACCU)Scope of Work Purpose Abbreviations References International Codes Project Specification HVACMEP Standards Responsibilities Project Manager Site Engineer QC Supervisor
METHOD STATEMENT for Installation of Air Cooled Condensing Unit (ACCU)Scope of Work
METHOD STATEMENT for Installation of Air Cooled Condensing Unit
(ACCU)
Table
of contents
1.
Scope of Work
2.
Purpose
3.
Abbreviations
4.
References
4.1
International Codes
4.2
Project Specification
4.3 HVACMEP
Standards
5.
Responsibilities
5.1
Project Manager
5.2
Site Engineer
5.3 QC
Supervisor
5.4
The QC Inspector
5.5
The Safety Engineer/Inspector
5.6
The Site Supervisor/Foreman
6.
Safety
7.
Procedures
METHOD
STATEMENT for Installation of Air Cooled Condensing Unit+
METHOD STATEMENT for Installation of Air Cooled Condensing Unit (ACCU)Scope of Work
(ACCU)
1. Scope
of work
The scope of this
method statement is to define all activities and requirements necessary for
Air Cooled Condensing
Unit (ACCU), Heating, Ventilation and Air Conditioning (HVAC) System
at project in
are in full compliance
with project specifications, drawings and HVACMEP standards related to
installations
standards, verifying
Documents comply with HVACMEP
Typical Inspection Plan (HVACMEPTIP) related to installations.
2.
Purpose
The purpose of this
method statement is to describe the quality control procedure to be followed
During installation of
Air Cooled Condensing Unit (ACCU) at Expand Dhahran Residential
Community project at
Dhahran, KSA and to detail the instructions to be followed and the
documentation to be
employed in order to ensure that safe installation is executed in accordance
METHOD STATEMENT for Installation of Air Cooled Condensing Unit (ACCU)Scope of Work
with the project
specifications and standards.
3.
Abbreviations
MS : Method Statement
HVACMEP IC : HVACMEP
Inspection Checklist
HVACMEPTR : HVACMEP
Test Report
HVACMEPTIP : HVACMEP
Typical Inspection Plan
HVACMEPES : HVACMEP Engineering
Standards
RFI : Request for
Inspection
PID : Project
Inspection Department
HVACMEP : HVACMEP Project
Management Team
ITP : Inspection &
Test Plan
METHOD
STATEMENT for Installation of Air Cooled Condensing Unit
(ACCU)
NCR : Non Conformance
Report
HVACMEP : China Railway
Construction Corporation
PM : Project Manager
CM : Construction
Manager
PPE : Personal
Protective Equipment
QA/QC : Quality
Assurance/Quality Control
4.
References
4.1
International Codes
§ ANSI -
American National Standard Institute
§ ASTM -
American Society for Testing and Materials
§ ASME -
American Society of Mechanical Engineers
§ ASHRAE
- American Society of Heating, Refrigeration and Air Conditioning
§ Engineers
§ NEMA -
National Electrical Manufacturer’s Association
4.2
Project Specification
§ HVACSECTION
15670 – AIR- COOLED CONDENSING UNITS
4.3 HVACMEP
Standards
§ 17-HVACMSS-503
NEMA Frame Motors.
§ HVACMEPES-HVAC-001
Heating, Ventilating and Air-Conditioning
§ HVACMEPES-HVAC-100
HVACMEP Mechanical (HVAC) Code
§ HVACMEPES-HVAC-101
Regulated Vendor List for Heating, Ventilating
and Air Conditioning
(HVAC) Equipment
(ACCU)
5.
Responsibilities
5.1
Project Manager
§ To
ensure that all preparation and application works are carried out according to
that contact
specifications, method statement, HVACMEP Engineering Specification
and manufacturer data
sheet.
§ To
ensure that the progressing of work is carried out according to the planned
program and as per the
approved Method Statement
§ To
ensure that all the manpower, equipment and materials required to execute the
Work are available
§ To
ensure that all related quality procedures are practiced and implemented
§ To
ensure that all safety matters related to this procedure are being observed
5.2
Site Engineer
§ Coordinate
all the site activities in accordance with approved IFC, Shop drawings,
project specification,
approved method statement and HVACMEP Engineering
Standards.
§ To
provide all necessary information and distribute responsibilities to his team.
§ To
monitor the progress of work in relation with work program and to report to
the PM.
§ To
ensure that the installer is well trained for this type of work.
§ To
coordinate with safety officer and to ensure that the works are carried out in
safe
practicing method.
§ Site
engineer shall inform mechanical Quality Control Inspector for internal
inspection
to check work has been
done accordance to IFC, Shop Drawings, HVACMEP
standards prior to preparing internal RFI for inspection and the time schedule.
METHOD
STATEMENT for Installation of Air Cooled Condensing Unit
(ACCU)
5.3 QC
Supervisor
§ Guide
the QC Inspectors and monitor their performance at the site
§ Provide
his subordinates with latest approved procedures, material submittals and shop
Drawings.
§ Shall
maintain proper filing for reports, RFI and NCRs.
§ Maintain
records of quality control check sheets/ reports for site tests and
inspections.
§ Coordinate
with PMT representative the required witnessing of inspection and tests.
§ Carry
out surveillance so as to ensure that personal are working in accordance with
approved method
statement.
§ Assurances
of approved methods are being used for testing and material recipient
inspection.
§ Verification
of material approval and vendor clarification.
5.4 The
QC Inspector
§ To
ensure full compliance of the work with the related approved method statement
§ Responsible
to ensure that the correct, approved sizes and dimensions.
§ Ensure
that IFC drawings, Shop drawings displayed on site during installation
inspection.
§ Ensure
that the materials being delivered to site and used are in accordance with
the project
specifications, approved material submittal and material receiving RFI.
§ Shall
be responsible for the inspection, preparation of RFI all documents and
compiling them for the
inclusion in the final documentation packaged.
§ To
maintain comprehensive inspection and test records for the purpose of
reference and
documentation.
§ Ensure
arrangement and location of latest released for construction drawings, and
specifications.
METHOD
STATEMENT for Installation of Air Cooled Condensing Unit
(ACCU)
§ Ensure
that tools/ equipment used for testing and commissioning purpose is calibrated
and certificates
available. (Certificate of calibration tool will be provided during
inspection time
separately).
5.5
The Safety Manager / Inspector
§ Ensure
that the work is performed under the safety measures of the approved HSE
plan.
§ Prior
to the commencement of any activities, work force will receive Tool Box on the
project safety
requirement .This tool box talk will include both activity issues as well
as general safety
requirements.
§ To
maintain continuous inspections of the site activities, advise and train the
Involved personnel on
daily basis to prevent accidents, personal injury or
Property damage.
5.6
The Site Supervisor/Foreman
§ Shall
have the knowledge of installation of Air Cooled Condensing unit (ACCU),
HVAC system in order to
explain the method statement to his subordinates.
§ To
ensure that work is carried out properly and according to manufacturer
Recommendations and
instructions received from the site engineer.
§ To
ensure that tools, labor and materials are available.
6.
Safety
§ Prior
to the commencement of any activities the work force will receive Tool box Talk
on the project safety
requirements. This tools box talk will include both activity issues
as well as general safety requirements
METHOD
STATEMENT for Installation of Air Cooled Condensing Unit
(ACCU)
§ Direct
supervisor will ensure that Protection Equipment’s, PPE, are used by site
personnel at all times
during this activity
§ Coordinate
fully with the safety officer in order to maintain safe working
Condition and proper
housekeeping of the site.
§ All equipment
and accessories have been certified for their capacity and integrity.
§ Safety
and risk assessment shall be performed for every job or task, which has the
potential for harm.
§ All
personal are issued with personal protection equipment.
§ Care
should be taken while lifting loads.
§ All
electrical connections shall be mechanically and electrically sound.
§ Should
not impose any appreciable mechanical strain on fixing of the connection and
shall not cause any
harmful mechanical damage to the equipment.
§ Transport
material in stacked condition and secure all loads adequately before transport.
In case of loading by a
loader, no one shall be present inside the vehicle. Do not keep
the truck in running
condition while loading.
§ Inspect
crane and all lifting tools and tackles before use. Never over load lines
obstruct
the equipment movements
in case it happens take proper isolation permit from
responsible project
engineer.
§ No one
should move under load at any circumstances. Engage only experienced to
make lifting
arrangement.
§ Select
correct type of pulling/ lifting equipment and do not overload the tackles.
7.
Procedures:
METHOD
STATEMENT for Installation of Air Cooled Condensing Unit
(ACCU)
2. Remove shipping
screws on wooden pallet and after removing the pallet re-fix the screws.
3. When installing the
unit, allow sufficient space around the unit for air circulation, wiring,
refrigerant piping,
and servicing. The clearance must be 48 inches (1219 mm) (min.).
4. Above the unit the
condensing fans must not be obstructed for airflow clearance and
maintenance.
5. Anti-vibration pads
(rubber-in-shear) or other vibration mounts (spring type) are recommended,
especially for roof
top installation and adjacent to occupied areas. The number of pads or spring
isolators shall be as MANUFCATURER
recommendations.
6. Ensure that the
unit is clean and free from any foreign material.
7. Install the
refrigerant line. See piping Installation procedure.
8. Install electrical
and control wiring in accordance with unit wiring diagrams, NEC and local
standards.
9. Check the unit installation, clean
the unit removing all work materials and debris.__

No comments:
Post a Comment
Please do not enter any spam link in the comment box