METHOD OF STATEMENT
FOR CHILLED WATER PIPING PART 2
![]() |
| METHOD STATEMENT FOR CHILLED WATER PIPING PART 1 FOR PROJECT STANDARDS AND FOR PROJECT INSTALLATION DETAILS THA HOW TO DO INSTALLATION AND WORK |
I. INSTALLATION GENERAL REQUIREMENTS:
I.1 Check and ensure all drawings used for installation are
latest and approved for construction.
I.02 Mark the pipe routing and support locations on the
ceiling as per approved drawings.
I.3 Check the co-ordination of piping layout with other
services and reflected ceiling and decide pipe route with minimum bends /
offsets.
I.4 Check and ensure sufficient clearance around pipe is
available for insulation.
I.5 Check the access and clear space around valves, vent
points, drain point’s locations for maintenance and servicing.
I.6 Fabricate the structural supports from G.I.
angles/channel as per support schedule as required.
I.7 After consultant or site engineer representative
inspection. Prior to installation clean all pipes and apply primer / red
oxide.
j. CHILLED WATER PIPES INSTALLATION
PROCEDURES
METHOD STATEMENT FOR CHILLED WATER PIPING PART 2
J.01 Drill the holes in the slab / shaft for fixing supports.
J.02 Fix the anchors and threaded rods with hangers / structural
supports as applicable. Threaded rod length shall be sufficient to allow
for leveling of piping.J.03 Cut the pipes accurately to measurements determined
at site.
J.04 Prepare the pipe ends according to the type of joints i.e.
Threaded joints, welded joints / grooved coupling joints.
J.05 The end preparation shall be done at site work shop.
J.06 Threading & grooving as applicable shall be done as per
fittings / couplings manufacturer's recommendations.
J.07 End preparations for welded joints shall be done as per approved
welding procedure.
J.08 After the end preparation clean the pipe ends and ensure no
material and dust are left inside.
J.09 Qualified and approved welders by consultant shall be engaged in
welding works.
J.10 Install the pipe spools at heights as per approved drawings in a
neat and tidy manner.
J.11 Insert the approved hard insulating material of suitable
thickness between the pipe and support.
J.12 Align and level the piping as per approved drawings.
METHOD STATEMENT FOR CHILLED WATER PIPING PART 2
J.13 Install supports for horizontal and vertical as per schedule of
supports.
J.14 Sleeves / openings of suitable sizes shall be provided at wall
crossings.
J.15 Expansion couplers shall be installed at locations where piping
crosses building expansion joints.
J.16 Install the piping connections with valves and accessories
wherever equipment are installed.
J.17 For AHU’s and FCU’s, not installed, complete the by-pass
connections as per approved drawing.
J.18 Fix the blind plugs / temporary valves on all drain,
air vent, pressure gauge, thermometer, and test points tapings as applicable.
J.19 Check and ensure proper supporting is provided as per
approved drawings.
J.20 Make temporary tapping provisions at multiple points
for easy and quick filling and draining of pressure testing water.
J.21 Ensure all joints are properly tightened.
J.22 During initial
water filling, employ sufficient man power to monitor the entire length of
the piping system for possible leakages.
J.23 If leakages are observed, arrest the leakages
immediately. If leakages are major, isolate the leaking portion with
nearest isolating valve and / or stop the water filling.
J.24 Ensure no leakages throughout the entire piping
system.
J.25 Observe leakage and pressurize the system using
hydraulic test pump.
J.26 During pressurization observe the joints and entire
piping system for leakages.
J.27 Pressure the system till pressure on the pressure
gauge at lowest part of the system indicates the 1.5 times the maximum
working pressure of the system under testing. (100 psig/690kpa)
J.28 During hot ambient conditions system pressure may
raise due to increase in the ambient temperature. Ensure under no
circumstances the system is pressurized above 1.5 times the maximum
working pressure. (100 psig/690kpa)
J.29 observes the pressure gauge readings for 6 hours and
ensure that there are no leakages.
J.30 the hydraulic pressure testing shall be witnessed by
consultants.
J.31 Proceed with insulation only after satisfactory
completion of hydro-static pressure testing.
K. INSULATION OF CHILLED WATER PIPES
K.01 For all pipe sizes, insulation pipe section of
suitable thickness, as per approved drawings / submittals may be used.
K.02 Pipe surface should be cleaned and made free from dust
and Grease. Insulation to be applied only when at normal temperature.
K.03 Adhesive of even coat is applied on the inner surface of the insulation
section.
K.04 Pipe section is slipped over the pipe longitudinal joints of pipe
section is sealed with an overlap of aluminum foil. Avoid longitudinal
joints facing upwards.
K.05 adjoining sections of insulation is butted firmly together by
application of adhesive on the sides.
K.06 Cut slices of insulation and slip it firmly between joints to ensure tight
packing of joints.
K.07 Seal all joints with aluminum tape.
INSULATION OF
VALVES AND FITTINGS
K.08 Insulate valves, strainers, flanges and other fittings with
identical material thickness and finish like the piping insulation
K.09 Fill all edges with filler sliced from the same insulation
material and ensure no air gaps.
K.10 For site shaping of sections cut, scrape, or miter to fit
contour of pipe fitting or valve.
K.11 For insulation of elbows cut one or more wedge shaped slices and
fix firmly. Pack joints with slices of insulation.
K.12 When insulating flanges and flanged fittings the insulation
cover to extend at least 50 mm onto the adjacent pipes to permit easy
stripping of insulation to attend to valve for maintenance.
K.13 Insulate strainers to permit removal of mesh without
disturbing the insulation of strainer
L. PRE-INSULATED PIPING INSTALLATION
PROCEDURE
A.
All materials shall meet or exceed all applicable
referenced standards, federal, state and local requirements, and conform to
codes and ordinances of authorities having jurisdiction.
B.
Pre-insulated Piping:
1.
All
straight sections of steel pipe shall be factory insulated. Field weld joints
shall be provided with field insulation kits to be compatible with the
pre-insulated pipe.
2.
The
carrier pipe shall be concentrically located within the jacket.
3.
Carrier
pipe shall be standard weight, carbon steel, seamless, ASTM A-53, Grade A, sch 40.Pipe;
all piping shall be shipped from the factory to the job with ends capped.
4.
Provide
polyurethane insulated underground carbon steel core piping system with HDPE
outer shell. The pre-insulated pipe
shall be in unitized factory prefabricated sections. Pipe shall be listed suitable for use with
38°F chilled water.
5.
Sock-o-lets
for vents, drains, instrument taps and thermowells shall be located in each
valve pit per plan and shall be welded on in the shop. Insulation shall be held back from such fittings
to allow field installation of nipples and instruments.
6.
Insulation. The insulation shall be formed-in-place
closed-cell polyurethane foam providing intimate contact with both the core
pipe and casing pipe. It shall be 90-95
percent closed cell structure per ASTM D2856, compressive strength 3.5 kg/sq
cm. 40 psi; thermal conductivity of 0.14
BTU-in/hr. ft2 F (.0202 w/m-0K) at an initial temperature 75 0F (240 C) per
ASTM C518 and 3.5 kg/sq cm. (40 psi) compressive strength per ASTM D1621.
7.
After
hydrostatic testing of the carrier pipe, field joints shall be insulated, with
kits provided by the pre-insulated pipe manufacturer. Field joint insulation shall be applied in
straight sections by pour foaming in-situ, using molds furnished by the system
manufacturer. Field joint insulation surface shall be sealed with a heat
shrinkable sleeve. Insulation and jacket on all fittings shall be factory
applied after pipe spool fabrication, extending continuously onto adjoining
straight section(s) of pipe.
8.
Underground
piping shall be bedded in compacted sand. Cover with densely compacted
backfill. Piping trench for a distance
of 8'-0" out from building shall not have pea gravel or sand but shall be
select backfill densely compacted as specified for building floor slab
backfill.
9.
Prepare
shop drawings to scale indicating the entire site plan with all underground
piping thereon. Elevations of all piping
shall be indicated. Details of piping
and bedding shall be drawn indicating size materials and arrangement. All shop
drawings shall be submitted to the pipe manufacturer for their review and shall
bear their stamp of approval prior to A/E review. Excavation for and laying of pipe shall not
be started until these shop drawings are approved.
10.
Prior to
fabrication, the Contractor shall review drawings of all disciplines, visit the
site and make on-site measurements to ascertain that no interferences will be
encountered upon installation. If there
are any significant deviations from the Contract Drawings, produce "Interference
Drawings." Before fabricating the
piping and installing related equipment, the Contractor shall send a letter to
the Owner stating that no interferences exist in the proposed installation. By submitting this letter, the Contractor
certifies that he has performed the above requirements and no interferences
will result during installation. There will be no additional compensation for
minor deviations.
11.
Piping
has a design pressure of 150 psig and shall be tested at a pressure of 225
psi. Test only one line at a time. Isolate piping from building and existing
system during tests. Do not insulate field weld joints until after hydro test.
A.
Factory technical assistance shall be provided by an
authorized representative of the manufacturer.
The representative shall be thoroughly qualified in knowledge and
experience in the proper installation methods of this type of piping system

No comments:
Post a Comment
Please do not enter any spam link in the comment box