MAINTENANCE AND CONTROL OF TRAFFIC
PART
1 - GENERAL
1.1 REQUIREMENTS INCLUDED
A. The Contractor shall provide, by the
installation of detours and/or traffic control devices and by the use of
flagmen, for the safe uninterrupted flow of vehicular and pedestrian traffic
through contract sites unless otherwise provided for in the contract documents,
or unless otherwise approved or directed by the Owner.
B. Related
Requirements:
1. General
Condition : Laws, Regulations and Fees 2. General Condition : Interference
with Traffic and Damage to Neighboring properties 3. Special Condition : Contractor-Prepared
Plans, Specifications, and Drawings 4. Special Condition : Local
Conditions 5. Special Condition : Protection
of Property 6. Section01040 : Coordination with
Others 7. Section01340 : Shop
Drawings, Samples and Miscellaneous Submittals
1.2 SCOPE OF WORK
A. Unless specifically provided for elsewhere
in the contract documents, the Contractor shall procure, furnish, construct
and/or install, maintain and remove all material, equipment, and labor; and
shall perform all work involved in providing for and maintaining the
uninterrupted flow of vehicular and pedestrian traffic through the contract
construction sites, including detours, temporary pavement, temporary
structures, temporary drainage facilities, traffic control devices, dust
control and removal of permanent and temporary pavement markings. Work shall also include preparing and
obtaining approval of drawings. Traffic
control devices shall include speed bumps, rumble strips, and barrels; control,
parking, street names, directional, regulatory, warning, detour, and danger
signs and signals; temporary barricades and guard rails; paint, posts, lumber
and hardware; temporary lighting, overhead warning signs, pavement markings and
flashing lights; flags, personnel safety equipment and apparel, and flagmen;
and electrical generators and batteries.
B. The Contractor
shall be responsible for anticipating changes in traffic conditions, and shall
be responsible for modifying or revising traffic control facilities and traffic
control devices in response to changes in traffic conditions and in
environmental conditions. 2 1.3 DEFINITIONS
A. Detour:
A temporary road or walkway maintained for safe public vehicular or
pedestrian traffic through or around a construction or other hazardous areas.
B. Traffic Control Device: A sign, signal, marking or device placed on,
over or adjacent to a vehicular or pedestrian walkway to warn, regulate or guide
traffic.
1.4 REQUIREMENTS OF LOCAL AND REGULATORY
AGENCIES
A. Ministry
of Communications of the
B. HVACMEP Owner "Traffic Detour and
Temporary Road Crossing Approval"
C. Contractor shall obtain a
"Construction Excavation Permit" from the Owner prior to starting any
temporary traffic control or road work.
1.5 REFERENCES AND STANDARDS
A. Standards for Road Safety Features are
published by the Maintenance Department of the Ministry of Communications of
the hereinafter referred to as MOC standards.
B. Detours, traffic control devices, and
traffic control procedures shall conform to the MOC standards, supplemented by
the HVACMEPGuidelines for Maintaining Traffic During Street and Highway
Construction and Maintenance Operations.
1.6 SUBMITTALS
A. Traffic
Plan:
1. Not later than
90 days after the effective date of the contract Notice to Proceed, and not
later than 21 days before beginning any activities for which the contract
requires the Contractor to provide for the safety and flow of traffic,
whichever results in the earliest date, the Contractor shall submit to the Owner
for approval a traffic plan with complete documentation of its plans for all traffic
control required to prosecute the contract work. The traffic plan shall include
both textual descriptions and layout drawings of locations, traffic patterns,
traffic channelization, traffic control procedures and traffic stages or
sequences which the Contractor proposes to implement in order to prosecute the
contract work.
2. The approval of
the traffic plan by the Owner shall be considered as general, and such approval
shall not be construed: a. As permitting any departure from the
contract requirements.
b. As relieving
the Contractor of the responsibility or liability for any errors or omissions.
c. As approving departures from standards
referred to herein.
B. Working
Drawings:
1. The Contractor
shall prepare working drawings for each traffic location, traffic pattern,
traffic channelization, and traffic stage or sequence. The working drawings
shall contain complete details of detours, road crossings by Contractor's
operations, infringements of traveled ways by Contractor's operations, traffic
control devices, and flagging proposed by the Contractor. The Contractor shall
deliver one (1) sepia, three (3) prints of the working drawings, and plus
CD-recordable ( CD-R) disks with ISO or equivalent format, which allows to read
the disk in most standard CD-ROM drives to the Owner, with a letter requesting
review and tentative approval of the working drawings, not later than 21 days
before the Contractor's scheduled date for activation of each traffic pattern,
traffic channelization, and traffic stage or sequence at each location.
2. The Owner will
review the working drawings, add comments as necessary, and return two prints
of the drawings, with comments, marked "TENTATIVELY APPROVED." Such tentative approval shall be considered
as approval to construct or install traffic control facilities and traffic
control devices in accordance with the Contractor's working drawings modified
to conform to the comments made by the Owner. However, tentative approval shall
not be considered as approval for the Contractor to activate the constructed or
installed traffic control facilities and traffic control devices. Activation
will not be permitted until after the Owner has inspected and given final
approval to the drawings and installations.
1.7 INSPECTION AND ISSUANCE OF APPROVAL
A. Notification: The Contractor shall complete all
construction and/or installation of traffic control facilities and traffic
control devices, and shall deliver notification to the Owner that the
facilities and devices are complete and in place not later than 72 hours before
the Contractor's scheduled activation of the facilities and devices.
B. Inspection: The Owner will inform the Contractor of a
scheduled time for inspection of the subject traffic control facilities and
devices. The Contractor's authorized
representative shall participate in the inspection with the Owner's
representatives. The inspection group
shall:
1. Determine
whether the details of the tentatively approved working drawings have been
implemented. Deficiencies, if any, shall be noted.
2. Examine the
entire traffic control facility and devices critically to determine whether
current environmental conditions and/or traffic conditions have changed from
the conditions anticipated in the working drawings, and whether such changes
necessitate revisions to the subject facility and devices.
C. Response to
Inspection: Appropriate modifications,
revisions and/or comments shall be made on the working drawings by the
Contractor and the inspection group, and the Contractor shall implement subject
modifications, revisions and/or comments.
The Contractor shall submit one (1) sepia and three (3) prints of the
subject drawings to Owner for approval.
D. Approval: The Contractor shall not interrupt or alter
the flow of traffic without prior written approval from the Owner, accompanied
by two (2) prints of the modified or revised working drawings and comments
stamped "Work May Proceed - Minor Comments" or "Work May Proceed
- No Comments."
1.8 RESTORATION OF SITE
A. Upon completion of the need for temporary
facilities and devices required by this section, the Contractor shall remove
all such temporary facilities and devices and shall dispose of them in
accordance with the requirements of the contract conditions.
B. Upon completion of removal of temporary
facilities and devices, the Contractor shall restore the site location to
either:
1. Meet the requirements of construction
to be performed under this Contract, or
2. Meet the
requirements of the drawings and specifications of the Contract under which the
site was originally improved.
|