SUB GRADE AND ROAD BASE, APPLICABLE CODES
AND STANDARDS, AMERICAN SOCIETY FOR TESTING AND MATERIALS, PARTICLE SIZE
ANALYSIS OF SOILS, LIQUID LIMIT OF SOILS, PLASTIC LIMIT AND MALLEABILITY INDEX
OF SOILS, DENSITY OF SOIL IN SITU BY THE SAND-CONE METHODOLOGY, MOISTURE
DENSITY RELATIONS OF SOILS AND SOIL-AGGREGATE MIXTURES MISTREATMENT TEN POUND.
(4.54 KG) RAM AND EIGHTEEN IN. (457MM) DROP TESTS, RELATIVE DENSITY OF COHESION
LESS SOILS, DENSITY OF SOIL IN SITU BY THE RUBBER-BALLOON METHODOLOGY,
SUB GRADE AND ROAD BASE
PART one – GENERAL
1.1 DESCRIPTION
This section covers the specification, trimming, compaction,
protection, reconditioning and testing of subgrade and roadbases before the
appliance of ulterior construction layers.
1.2 SECTION
INCLUDES
This section covers the furnishing of materials,
instrumentality and labour for excavating, trimming, wet learning, protection,
dirt management and compaction of sub grades and road bases.
1.3 RELATED
SECTIONS
02200 Earthwork
1.4 RELATED
OBLIGATIONS
A. the final
necessities below Division one apply to figure per the section.
B. The
Contractor shall examine all different sections of the specification for
necessities which can have an effect on work of this section.
C. The
Contractor shall coordinate work with all different trades touching or stricken
by activities of this section. get together with such different trades to
assure the steady progress of all operations below the Contract
1.5 APPLICABLE
CODES AND STANDARDS
The following codes and standards square measure meant to
produce a suitable level of quality because the documented codes and standards
to be submitted by the Contractor to the Owner for approval ahead of their use.
ASTM American
Society for Testing and Materials
D 422 Particle Size
Analysis of Soils
D 423 Liquid Limit
of Soils
D 424 Plastic Limit
and malleability Index of Soils
D 1556 Density of
Soil in situ by the Sand-Cone methodology.
D 1557 Moisture
Density Relations of Soils and Soil-Aggregate Mixtures mistreatment ten pound.
(4.54 kg) ram and eighteen in. (457mM) Drop Tests.
D 2049 Relative
Density of Cohesionless Soils
D 2167 Density of
Soil in situ by the Rubber-Balloon methodology
D 653 Definition of
Terms and Symbols about Soil and Rock Mechanics
BSI British
Standards Institute.
BS 812 Methods for
sampling and testing of mineral aggregates, sands and filters.
BS1377 ways for
testing soils for technology functions.
BS6031 Code of apply
for Earthworks
1.6 SUBMITTALS
A. methodology
STATEMENT AND PROGRAMME
The Contractor shall give the Owner with the subsequent
information:
a. methodology
STATEMENT: shall embrace planned excavation and compaction plant, methodology
of excavation, filling and compaction, methodology of treating slopes,
protection of formations, etc.
b. PROGRAMME
OF WORKS: a minimum of fourteen days before the beginning of the Works.
1.7 QUALITY
management
A. REPORTING
INSPECTIONS AND APPROVALS
The Contractor shall befits any necessities of relevant
native authorities concerning the notification, review and approval of all
excavations and formation levels. The
Contractor shall keep dated records of the inspections and any directions, that
end in the outlined limits of the excavation being exceeded.
The Contractor shall offer the Owner AN united amount of
notice of the time every formation level are going to be exposed in order that
the Owner could, if he therefore needs, examine the formation. this era shall
be a minimum of twenty four hours.
The Contractor shall maintain, and replica to the Owner
occasionally to be united, full records of notices, inspections, and therefore
the time of formation exposure before covering up.
The Contractor shall maintain a professional representative
on-the-scene throughout all earthworks operations. Weekly internal control
Report are going to be equipped to the Owner summarising the following:
a. Daily
review reports
b. Soil
check results together with relative compaction (from previous week’s samples)
c. Water
quality tests
d. Samples
taken on (and quantity of labor painted by every individual sample)
e. internal
control performance
f. A
Monthly internal control Report are going to be equipped to the Owner
summarising the following:
g. Weekly
internal control report
h. management
charts (showing previous sixty days aforethought check results/control measure,
etc.).
i. planned
internal control programme enhancements, if acceptable.
j. Revisions
to frequency of testing
k. Work
suggested for acceptance
The Owner shall approve the monthly internal control Report
before being admit table as a contract record.
B. SETTING
OUT
The Contractor shall give full time dedicated surveyors and
technicians to undertake measure and for the presentation of results. The Contractor can give curricula vitae of
key personnel together with the pinnacle surveyor and technicians. If the Owner
believes for any reason that any of the personnel square measure unsuitable the
Contractor shall take away them from web site and quickly realize a
replacement.
The Contractor shall establish a top quality assurance
procedure to internationally recognized standards so as to assure the accuracy
of the popping out and quality of the data. A freelance company approved by the
Owner shall undertake monthly audits. Audit reports are going to be issued on
to the Owner.
All plans and cross sections shall be bestowed to the Owner
in AutoCAD 2006 dwg format. Access to
the digital records are going to be needed in any respect time by the
Owner. The Contractor shall agree the
format of drawings and therefore the system of digital documentation management
with the Owner.
PART two – product
2.1 DEFINITIONS
A. FORMATION
Formation shall mean the surface of the bottom once
completion of any excavation or filling operation.
PART three - EXECUTION
3.1 FORMATIONS
A. PROTECTION
To avoid injury to excavation formations, excavation surface
shall be left a minimum of 150mm on top of formation level till like a shot
before being offered for review. Oozing and water shall be unbroken off the
works as nominal.
Construction plant and different traffic shall not be
operated on the formation, aside from that needed for preparation of the
formation, unless adequate protection is provided. The Contractor's proposals for making ready
the formation and particularly however he intends to traffic it shall be united
with the Owner.
If any square measures of formation are broken by the
weather or the other cause the Owner shall be like a shot notified.
The Contractor shall not permit any formation to be left
exposed for over four hours once being uncovered.
B. PREPARATION
All formations shall be cut, levelled, cleared of loose
material and compacted, in accordance with the Specification, prepared for
review.
After removal of any protection layer and unless otherwise
directed, road formations shall be now compacted in accordance with this Specification.
Before installation of A1a appropriate fill, material is to be compacted or
existing subgrade to be compacted to needed elevation. The compaction technique
shall, for this purpose, be assumed to be as for a layer of 300mm finished
thickness compacted in compliance with this Specification.
Immediately when this compaction, the formation shall be cut
to attain the desired tolerances.
After trimming, or re-trimming if necessary, the formation
shall be rolled with a minimum of 1 pass of a smooth-wheeled roller having a
mass per meter dimension of roll not but 2100kg, or, a vibrating roller having
a mass per meter dimension of not but 700kg or a moving plate compactor having
a mass per m² below the bottom plate of not but 1400kg. The primary layer of
building shall cowl it now when review.
3.2 DUST
management
The Contractor shall
a. Use all
means that necessary throughout the world of the location below the occupation
of the Contractor to regulate dirt on and close to the work and on and close to
all borrow areas.
b. completely
moisten all surfaces pro re nata to stop dirt being a nuisance or a hazard to
the occupants of the prevailing properties, and to the general public and
synchronous performance of alternative
work on website.
3.3 CONTROL OF
WATER
The Contractor shall:
a. Keep all
work well drained in the slightest degree times and make sure that all work is
meted out in unsaturated conditions in accordance with the “Method Statement”
for the management of water as ready and suggested by the Contractor and
approved by the Owner.
b. Construct,
operate, and maintain wells, sumps, pumps, relief well systems, evacuation
channels, pipelines and culverts, necessary for excluding water from the work
to confirm stability of excavations, whereas construction is ongoing. Such temporary works and plant shall embrace
spare units unbroken prepared for immediate use just in case of breakdowns, and
shall not be removed while not the approval of the Owner. All pipelines, culverts and instrumentality
not toward land within the possession of the Contractor shall be fitly designed
for Construction traffic.
c. create
provision for the discharge or disposal from the work of all water and waste
product howsoever arising and supply temporary pipes, flumes or channels.
The Owner reserves the proper to direct the Contractor to
put in, operate and maintain evacuation, pumping systems and well systems
whenever, within the opinion of the Owner the ways getting used by the
Contractor to regulate water area unit inadequate, nonetheless any previous
acceptance of such ways. No extra
payment shall be created for evacuation systems put in, operated and maintained
at the direction of the Owner.
3.4 TESTING
Testing of formations shall be meted out in accordance with
section 02315.
3.5 TOLERANCES
The permissible deviations of the formation levels as
outlined during this Specification from the positions shown or determinable
from the drawings and with regard to the closest information level shall be as
follows:
PERMISSIBLE DEVIATIONS OF FORMATION LEVEL
Beneath road and parking lot construction + 20mm - 30mm mound and cutting
slopes and pedestrian footways (unsurfaced) ± 50mm.